Stock Markets May 26, 2026 08:54 AM

TeraWulf Expands Kentucky Footprint with Muskie Data Campus Purchase

New Eastern Kentucky site adds more than 1 GW of potential HPC capacity; shares climb 8%

By Nina Shah WULF

TeraWulf Inc. (NASDAQ: WULF) saw its stock rise 8% after announcing the acquisition of the Muskie Data Campus in Eastern Kentucky from Industrial Equity Partners. The 285-acre parcel within EastPark Industrial Park is positioned to support over 1 gigawatt of hyperscale AI and high-performance computing capacity, with staged deliveries of 500 megawatts beginning in the second half of 2028 and a further 500 megawatts targeted for the second half of 2030. Kentucky Power is building a 345 kV substation tied into the existing 765 kV network.

TeraWulf Expands Kentucky Footprint with Muskie Data Campus Purchase
WULF

Key Points

  • TeraWulf acquired the Muskie Data Campus in Eastern Kentucky from Industrial Equity Partners, prompting an 8% jump in its stock.
  • The site includes approximately 285 acres within the 1,000-acre EastPark Industrial Park and is expected to support over 1 gigawatt of hyperscale AI and HPC capacity, with 500 MW ramping from H2 2028 and 500 MW targeted in H2 2030.
  • Kentucky Power is building a 345 kV substation tied to the existing 765 kV transmission network; transmission and energy service agreements were executed with Industrial General Service tariff provisions.

TeraWulf Inc. (NASDAQ: WULF) shares rose 8% on Tuesday after the company disclosed the acquisition of a large-scale development site in Eastern Kentucky intended for hyperscale high-performance computing and AI infrastructure.

The property, named the Muskie Data Campus and purchased from Industrial Equity Partners, is described by TeraWulf as capable of supporting more than 1 gigawatt of data center capacity over time. The company outlined a staged delivery plan: the initial 500 megawatts are expected to begin ramping in the second half of 2028, while an additional 500 megawatts are targeted for delivery in the second half of 2030.

Located inside the 1,000-acre EastPark Industrial Park, the site encompasses approximately 285 acres of owned and controlled land that the company says can support hyperscale AI and HPC deployments. Utility infrastructure work is already in progress: Kentucky Power, an AEP Company, is constructing a 345 kV substation that will connect to the existing 765 kV transmission network.

Paul Prager, Chairman and Chief Executive Officer of TeraWulf, framed the purchase as consistent with the companys stated strategy. "This acquisition further reinforces the strategy we discussed on our first quarter earnings call: securing and developing large-scale, power-advantaged sites capable of supporting the next generation of HPC workloads," he said.

The Muskie Data Campus arrives pre-zoned for its intended use and TeraWulf reports permitting work is underway. According to the company, only limited site work is required to enable data center construction. Transmission infrastructure and energy service agreements were executed at the time of the acquisition pursuant to the applicable Industrial General Service tariff structure for large loads.

This purchase marks TeraWulfs second major digital infrastructure campus in Kentucky. It joins the firms existing 480 MW Justified Data campus in Hancock County.


Context and implications

The transaction adds a sizeable development footprint to TeraWulfs pipeline and pairs planned capacity with high-voltage transmission work already in motion. The company has provided target timing for staged delivery of capacity and completed utility and tariff agreements alongside the acquisition, while noting zoning and permitting are in process.

Risks

  • Timeline uncertainty - The company has set expected and targeted delivery windows (H2 2028 and H2 2030) for staged capacity, which are projections and may be subject to change.
  • Permitting and site readiness - While the site is zoned and permitting is underway with limited site work required, remaining permitting processes or site preparation could affect construction schedules or start dates.
  • Execution of infrastructure - Although transmission infrastructure and energy service agreements were executed concurrent with the acquisition, the realization of planned capacity depends on completion of the 345 kV substation and integration with the 765 kV network.

More from Stock Markets

U.S. Officials Held Early Talks on Taking Equity Stakes in AI Firms, NOTUS Says Jun 4, 2026 Japan Sees Real Wages Climb 1.9% in April; Household Spending Drops Less Than Anticipated Jun 4, 2026 Keystone Acquisition Completes $288.22 Million IPO and Private Warrant Placement Jun 4, 2026 U.S. Futures Slip as Tech Retreats; Markets Await Jobs Report Jun 4, 2026 U.S. Officials Hold Early Talks About Acquiring Equity Stakes in AI Firms Jun 4, 2026