Stock Markets June 10, 2026 12:40 PM

Black Hills Confirms Cheyenne Data Center Project Progress; Shares Rise

1.8-GW build moves forward with customer engagement after development partner change; service aimed for early 2028

By Marcus Reed
Share
Twitter Reddit Facebook LinkedIn
BKH

Black Hills Corporation said its planned 1.8-gigawatt data center power project in Cheyenne, Wyoming remains on track despite a change in development partners, prompting a 5.3% jump in the company’s shares. The utility is working directly with the potential large-load customer, has secured customer-funded milestone contributions exceeding $200 million, and has advanced substation agreements and regulatory filings as it prepares for service in early 2028.

Black Hills Confirms Cheyenne Data Center Project Progress; Shares Rise
BKH
Summarize with
ChatGPT Perplexity Claude Grok Gemini

Key Points

  • Black Hills confirmed the 1.8-gigawatt data center power project in Cheyenne, Wyoming remains active and expects service in early 2028.
  • Crusoe is no longer the development partner; Black Hills is now working directly with the prospective large-load customer.
  • The customer has provided more than $200 million in refundable contributions for milestone payments; the company has also executed a substation agreement and filed for a Certificate of Public Convenience and Necessity.

Black Hills Corporation saw its stock climb 5.3% on Wednesday after confirming that its 1.8-gigawatt data center project near Cheyenne, Wyoming continues to advance following a change in development partners.

The company stated that, although Crusoe is no longer serving as the development partner on the initiative, the project has not been paused and remains a priority. Black Hills has shifted to working directly with the potential large-load customer to move the program forward and expects service to begin in early 2028.

Company statement

In a public comment, Linn Evans, president and CEO of Black Hills Corp., said: "We remain committed to supporting the project’s data center customer and delivering the infrastructure necessary to meet their long-term energy needs. The 1.8-gigawatt project has not been paused and continues to represent a significant opportunity for the company."

Recent commercial and regulatory steps

According to the company, in April 2026 its Wyoming electric utility subsidiary entered into an agreement with the prospective customer to procure long lead-time generation equipment. The prospective customer has provided in excess of $200 million in refundable contributions in aid of construction to date; those funds correspond to milestone payments intended to secure generation equipment.

Black Hills also executed a substation agreement with the large-load customer and in January 2026 filed a Certificate of Public Convenience and Necessity for a substation to support the project. The company expects the data center load to be served under the Wyoming utility’s Large Power Contract Service Tariff.

Implications

The company framed the project as a meaningful opportunity for its business while signalling continued coordination with the prospective customer on financing and infrastructure commitments. Key steps completed to date include procurement arrangements for long lead-time equipment, customer-funded milestone contributions, a substation agreement, and the regulatory filing for the supporting substation.


The company’s updates reflect progress on commercial, supply chain and regulatory fronts as the project moves toward the timeline set for early 2028 service commencement.

Risks

  • Change in development partners introduces potential execution and coordination uncertainty for the project - impacts utilities and infrastructure delivery.
  • Project relies on the prospective large-load customer’s milestone-funded contributions to secure long lead-time generation equipment - impacts project financing and supply chain commitments.
  • Regulatory approvals are required for supporting substation infrastructure, evidenced by the Certificate of Public Convenience and Necessity filing - impacts timelines and utility service arrangements.

More from Stock Markets

Google debuts DiffusionGemma, a text model built for speed with parallel generation Jun 10, 2026 Ennoconn's 30% Stake Forces Mandatory €23.5 Cash Offer for Kontron Jun 10, 2026 Piper Sandler Starts Coverage of SharkNinja With Overweight, Cites Double-Digit Growth Potential Jun 10, 2026 Palantir CEO: Enterprise Clients Frustrated with Frontier AI Labs' Approach Jun 10, 2026 Energy Stocks Rally as Oil Gains on Geopolitical Tension and Inventory Drawdown Jun 10, 2026