VG March 2, 2026

Venture Global LNG Q4 2025 Earnings Call - Rapid scale-up clears path to $5.2B-$5.8B 2026 EBITDA

Summary

Venture Global used Q4 to turn promises into production. The company has quickly moved from IPO to large scale output, nearly tripling revenue and EBITDA year over year, while simultaneously building CP2 and finishing Plaquemines commissioning. Management frames the strategy as speed and modularity, monetized through a mix of long and intermediate contracts, project-level financing, and bolt-on expansions that could double monthly ship loadings by 2029.
The near-term picture is straightforward and conditional. 2026 guidance pins consolidated Adjusted EBITDA at $5.2 billion to $5.8 billion, assuming remaining cargos price in around $5 to $6 per MMBtu. Operational strengths include low O&M costs, controlled shipping, and access to discounted Permian gas at CP2. Key risks are arbitration noise, volatile short-term commodity and shipping markets, and near-term cargo disruptions from weather and geopolitics that already trim Q1 EBITDA by an estimated $500 million.

Key Takeaways

  • Venture Global went public in January 2025 and quickly commercialized assets, with Calcasieu Pass reaching commercial operations in April 2025.
  • Q4 2025 revenue was $4.4 billion, up from $1.5 billion in Q4 2024; full year 2025 revenue was $13.8 billion versus $5.0 billion in 2024.
  • Consolidated Adjusted EBITDA in Q4 2025 was $2.0 billion, a 191% increase from $688 million in Q4 2024; full year 2025 Consolidated Adjusted EBITDA was $6.3 billion.
  • Management says total assets rose about $10 billion to $53 billion in 2025, and income from operations nearly tripled year over year.
  • Venture Global is building at scale, simultaneously constructing more than 57 MTPA across projects, and projects combined could reach roughly 68 MTPA run-rate when Calcasieu Pass, Plaquemines, and CP2 phases 1 and 2 are complete.
  • Contracting progress: since reentering the market in April, the company has signed 9.25 MTPA of new 20-year SPAs; in 2025 it secured additional 7.75 MTPA of 20-year SPAs and announced a 0.5 MTPA five-year deal with Trafigura plus a 1.5 MTPA 20-year SPA with Hanwha.
  • For 2026, management guides to 486 to 527 total cargoes from both facilities, with 69% of expected 2026 production capacity already contracted, and Calcasieu Pass expected to export 145-156 cargos.
  • Plaquemines operational update: all 36 trains have had initial startup, the site is using temporary power while transitioning to permanent power in Q2, and Phase 1 COD is targeted for late 2026 with Phase 2 mid-2027. Plaquemines exported 234 cargos in 2025 and is projected for 341-371 cargos in 2026.
  • CP2 update: Phase 1 FID announced July 28, construction progressing on schedule and budget, six of 26 liquefaction trains on foundations, first LNG tank roof raised faster than industry precedent, $1.7 billion of equity invested in Phase 2, with project financing and FID expected imminently.
  • Management expects to fund project CapEx with construction loans and retained earnings, avoiding parent-level equity, preferred, or debt for now, and to retain 100% ownership of projects.
  • The company filed with FERC to increase peak liquefaction capacity at Plaquemines and CP2 to 35 MTPA, and sought approval for up to 31 MTPA of bolt-on expansion at Plaquemines.
  • Bolt-on strategy: two near-term bolt-ons at CP2 and Plaquemines are each ~6.4 MTPA, lower cost, faster to build, and could add roughly 13 MTPA of incremental capacity after CP2 Phase 2, helping reach ~90 monthly ship loadings by 2029.
  • Pricing and cash flow sensitivity: 2026 Consolidated Adjusted EBITDA guidance of $5.2B-$5.8B assumes $5-$6 per MMBtu for remaining cargos; a $1 per MMBtu move in fixed liquefaction fees would shift EBITDA by roughly $575M to $625M.
  • Plaquemines realized a $6.02 per MMBtu weighted average liquefaction fee on commissioning cargos in Q4; Calcasieu Pass realized an implied $2.01 per MMBtu in Q4, with 2026 Calcasieu guidance at an implied $1.98 per MMBtu including arbitration reserves.
  • Near-term headwinds: winter storm, shipping constraints, and higher Henry Hub pricing compressed margins in late Q4 and into Q1 2026, prompting a $500 million estimated hit to Q1 Consolidated Adjusted EBITDA; Q1 2026 EBITDA is now expected to be $1.15B-$1.25B.
  • Arbitrations: Repsol arbitration returned a favorable no liability outcome; management has reserved an estimated non-cash $13 million per quarter revenue reduction at Calcasieu Pass for remaining arbitration exposure, with BP arbitration likely unresolved until later next year.
  • Safety and operating efficiency claims: management reports project-level O&M costs about 30% below industry averages, construction timelines less than half industry norms, and a Total Recordable Incident Rate of 0.16 versus a national average of 2.2.
  • Market view: management expects demand to meet or exceed supply through the late 2020s and move to undersupply in the early 2030s absent new FIDs, basing long-term demand growth on a conservative 4.7% through 2035 versus historical 5.3%.
  • Logistics advantage: Venture Global controls a shipping fleet, reported at nine owned and chartered vessels with two more deliveries coming, which management says helps mitigate shipping rate volatility and move cargoes in tight markets.
  • Feedstock advantage at CP2: pipeline access to Permian Waha and Katy, combined with invested nitrogen removal units, is positioned to source gas at a material basis discount to Henry Hub, enhancing margins when operational.

Full Transcript

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: I will now hand the conference over to Ben Nolan, Senior Vice President, Investor Relations. Please go ahead.

Ben Nolan, Senior Vice President, Investor Relations, Venture Global LNG, Inc.: Thank you, John. Good morning, everyone, and welcome to Venture Global LNG, Inc.’s fourth quarter 2025 earnings call. I’m joined this morning by Michael Sabel, Venture Global CEO, Executive Co-Chairman, and Founder, Jack Thayer, our CFO, and other members of Venture Global’s senior management team. Before we begin, I would like to remind all listeners that our remarks, including answers to your questions, may contain forward-looking statements and actual results could differ materially from what is described in these statements. I encourage you to refer to the disclaimers in our earnings presentation, which is available on the investor section of our website. Additionally, we may include certain non-GAAP metrics such as Consolidated Adjusted EBITDA, which we may refer to simply as EBITDA during this call. A reconciliation of these metrics to the most relevant GAAP measures can be found in the appendix of the earnings presentation posted on our website.

The guidance in this presentation is only effective as of today. In general, we will not update guidance until the following quarter and will not update or affirm guidance other than through broadly disseminated public disclosure. I’ll now turn the call over to Michael Sabel.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Thank you, Ben. Good morning, everyone, thank you for joining us today. We are pleased to share our fourth quarter and full year 2025 results and provide guidance for 2026. I will begin the call with an overview of our key accomplishments and future plans before shifting to our LNG projects individually. I will then make some remarks on the LNG industry in the current events before turning over the call to Jack, who will provide a more detailed review of our financial results and guidance for 2026. Following all prepared remarks, we will open the line to Q&A. Turning to page 5 of the presentation, 2025 was a landmark year for Venture Global. In January, we went public. We reached commercial operations at our first project, Calcasieu Pass, in April.

At Plaquemines, after producing our first cargo at the end of December 2024, we have ramped up commissioning activities and are now generating more than one commissioning cargo per day. At CP2, our largest project to date, we launched construction and raised financing for the first phase in July. This means we are simultaneously constructing 57 MTPA plus of capacity across two facilities. Phase one of Plaquemines is on track for COD this year, and construction of the first phase of CP2 is running well and is on schedule and on budget. Total assets grew by approximately $10 billion to $53 billion, and EBITDA and income from operations nearly tripled.

Venture Global is on track to be the largest LNG producer in North America, supported by more than $134 billion of total contracted third-party revenue, which we expect to continue to grow as we add to our existing base of 49 MTPA of long and intermediate term offtake agreements. For 2026, it is worth noting that we now have 69% of expected production capacity contracted, a percentage that should rise quickly as we anticipate signing additional short to intermediate and long-term contracts in the near term. Our priority has been to control what we can control and deliver on what we promised. As you see on page 6, we have accomplished a great deal this year.

The number of cargoes we produced in 2025 was at the high end of the guidance range set out at the IPO. We reached FID at CP2 Phase 1. We secured 7.75 MTPA of additional 20-year SPAs. We leveraged data generation and analysis, lessons learned from Calcasieu Pass to further increase production capacity at Plaquemines. We identified low cost bolt-on production opportunities at our first three facilities in excess of what we had originally anticipated. In addition, as you can see in the column to the right, we believe there should be further upside to each of these areas in 2026, and we are working diligently to deliver growth in return for our shareholders and customers. The constant pursuit of excellence is core to our culture at Venture Global, as we have highlighted on page 7.

The combination of structural benefits from our modular approach, massive data capture and analysis, and our unrelenting focus on continuous learning and improvement translates into superior LNG production and project-level operating and maintenance costs that are currently about 30% below industry averages. We see room for further improvements. We have continued the process of bringing most of the typical EPC functions in-house, which has enabled us to construct our facilities in less than half the time many other LNG projects take, which, combined with our faster production ramp, translates into lower costs and better returns. While efficiency and speed are important objectives, our first priority remains the safety of our employees, contractors, and communities, as reflected in our best-in-class safety record.

We are working to monetize the key components of the LNG value chain and augment our LNG portfolio with complementary midstream shipping, regasification, and in the case of CP 2, nitrogen removal assets, all of which we expect should give us better access to attractively priced gas, protect and enhance margins, and improve our customer connectivity. We view our LNG infrastructure as technology assets that we are constantly optimizing to be safer, faster, and more efficient. You can see on page 8 our near-term outlook for the buildup of production from our facilities. We anticipate Calcasieu Pass, Plaquemines, and CP 2 phases 1 and 2, when complete, will generate approximately 68 million tons per annum plus on an annual run rate basis, with room for upside from optimization efforts and peak production opportunities. Of this 68 MTPA, we have contracted approximately 72% already on a long-term basis.

Beyond that, we have included what we anticipate will be our next additions following CP2, Phase 2. I’ll discuss in more detail shortly, we expect to be able to add approximately 13 MTPA of bolt-on capacity at CP2 and Plaquemines at costs well below even our own industry-low construction pricing and even faster than our industry-leading construction timelines. This tremendous growth in the number of trains and related infrastructure translates into a more than doubling of monthly ship loadings, growing from approximately 43 per month today to approximately 90 per month in 2029. This, in turn, could transform our cash flows. For example, assuming just a $3 per MMBTU liquefaction fee for our uncontracted volumes, we estimate by 2029 our EBITDA to be about $11 billion.

Assuming a $5 MMBTU on uncontracted volumes, that estimated EBITDA number could rise to $17 billion, reflecting the straightforward impact of installation of more trains producing more LNG commodity product. Our new production ramp is expected to be staggered with the COD dates of our existing projects, such that as we complete commissioning at one project and move to long-term fixed rate contracts, the new production capacity should begin to ramp, creating a balanced portfolio of long, intermediate, and short-dated sales agreements. This should improve cash flow visibility and provide an optimal balance of margin and predictable cash flow while importantly retaining very valuable upside earning optionality.

As we advance on schedule this year and next year to COD of phases one and two of Plaquemines and following CP2, we activate an increasing portion of our $134 billion of long-term contracted third-party revenue now blended with a growing portfolio of intermediate-term tenor sales contracts. We are actively working to add to both the 20-year and intermediate-term contract portfolios and anticipate more deals in the coming quarters. Importantly, we currently target funding all of our project CapEx and incremental growth with our existing construction loans, retained earnings, and incremental project-level borrowing with no parent-level equity preferred or debt anticipated at this time. Notably, we have executed our Plaquemines and CP2 construction financings while retaining 100% ownership of those projects and therefore, of course, 100% of future earnings. Turning to page 9.

Since we reentered the contracting market in April of last year, Venture Global has signed 9.25 MTPA of new 20-year SPAs with a fantastic portfolio of customers. This is more volume than any other LNG company in the market, demonstrating that the world’s top buyers trust our execution and reliability. Today, we are pleased to announce our first 5-year contract at Venture Global Commodities for approximately 0.5 MTPA with Trafigura. Additionally, last week we signed a new 1.5 MTPA 20-year SPA with Hanwha Aerospace, marking our first long-term contract with a South Korean customer. These two new binding agreements add to the four we signed in the fourth quarter of 2025 with Naturgy, Atlantic C, Mitsui, and Tokyo Gas. On page 10, I’ll highlight our performance in Q4 and the exceptional year-over-year increase in our results.

As you can see, we nearly tripled revenue, income from operations, and EBITDA through the gradual ramp of commissioning. Jack will discuss these numbers in greater detail later, but the main takeaway is our company’s ability in the fourth quarter to generate over $2 billion of EBITDA and $1 billion of net income during a period of disruptive market dynamics, including swings in commodity prices in a period of challenging ship availability, underscoring the resiliency of our business model and resourcefulness of our team. Turning to page 11. Thanks to our innovative temporary power solution, all 36 liquefaction trains at Plaquemines have undergone initial startup.

We also recently filed a request with FERC to increase the authorized peak liquefaction capacity at both Plaquemines and CP2 to 35 MTPA, as well as filing with FERC and the U.S. Department of Energy for up to 31 MTPA of bolt-on expansion at Plaquemines. Our construction success is predicated on our mission to be the safest LNG developer in the industry, as reflected by our 0.16 Total Recordable Incident Rate compared to the national average of 2.2. I mentioned on our commercial success, our commercial success in 2025 earlier and now early 2026. Our finance team is also very busy as we issued $3 billion of Plaquemines notes to repay construction financing, and we are currently hard at work to finalize the construction loan for Phase 2 to fully fund the construction of that phase of CP2.

Turning to page 13, we show a summary of the projects we are planning to bring online by the end of the decade. As I just discussed. As you know, there are further low-cost bolt-on and growth opportunities available to us, but we thought it would be helpful to outline our near-term development plans. Moving to page 14, it was business as usual at Calcasieu Pass during Q4, as we exported 38 cargoes, which is down slightly from our prior expectations as ship availability and Atlantic storm delays late in the quarter did impact several anticipated cargoes. I wanted to provide some update commentary on the Calcasieu Pass arbitrations. In January, we received a favorable no liability decision in the Repsol arbitration proceedings.

Going forward, the non-cash reserve, which reflects our best estimate of award outcomes from BP and the other three remaining arbitrations, is currently estimated to be $13 million per quarter reduction to revenue at Calcasieu Pass through the 20-year duration of the SPA contract terms. The impact EBITDA will be less due to adjustments for non-controlling interest and taxes. Importantly, this is an estimate, and there is no cash impact to our fourth quarter financial statements. We will update these estimates in our financials quarterly as we receive arbitration results and incorporate any final financial awards or settlements going forward. While BP has raised the quantum of their damages claim, our position as to our exposure there is unchanged, as the clear language of the contracts prevents recovery of the categories and magnitude of damages sought by BP. Turning to page 15.

Plaquemines continues to progress construction, commissioning, and the performance reliability and assurance testing required in advance of Phase 1 COD in Q4 of this year and Phase 2 COD in mid-2027. We continue to utilize and rely on a significant amount of temporary power, in the second quarter, we expect Phase 1 will transition to its permanent power plant configuration. We are yet to achieve substantial completion, but we are on schedule and targeting substantial completion under the scopes of the EPC by late summer, so coming soon. Turning to page 16, CP 2 is now just over 7 months from Phase 1 FID, announced on July 28. Despite this short period, I’m pleased to announce construction of Phase 1 is proceeding well on schedule and budget.

Over the weekend, we raised the roof on our 1st LNG tank, making it the fastest time to a roof raise of this size in the history of the LNG industry. Furthermore, we now have 6 of the 26 liquefaction trains delivered to the site and on foundations and expect delivery of the 1st pretreatment module in the coming months. With respect to phase 2, as I mentioned, we have now signed 5 MTPA of 20-year SPAs to support the financing for the project. We continue to have constructive conversations with off-takers and expect to announce additional SPAs in coming quarters. With $1.7 billion of equity already invested in phase 2, we expect project financing and FID to be complete in coming weeks.

We anticipate funding the entire CP2 project with retained earnings and a construction loan from a group of leading banks, enabling Venture Global to again maintain 100% ownership in one of the world’s largest LNG projects. On page 17, we depict the first 2 bolt-on expansions we expect to develop after FID of CP2, phase 2, subject to additional contracting and regulatory approval. The bolt-ons at CP2 and Plaquemines are straightforward liquefaction train and gas turbine additions that should add around 6.4 MTPA each. The additions leverage the benefits of our modular approach, resulting in what we expect to be much lower cost and much shorter construction timelines. These developments exemplify the advantages of our mid-scale modular approach, as well as the power to leverage existing redundancies built into the original designs. Turning to page 19.

The past few months and recent events have demonstrated the impact of seasonality, the inherent tightness of LNG supply and demand, of course, the impact of geopolitics on our market. While LNG spreads compressed in late 2025, cold weather in January and February has exhausted gas inventories in Europe to low levels, lifting LNG forward curves. This is all impacted by current events over the weekend. A number of LNG projects under construction have announced delays with their planned start dates. As you can see on the left, the forward curves reflect the market expectation for LNG prices in both Asia and Europe to remain at considerable spreads over Henry Hub through 2028, even during periods of expected cold weather and higher U.S. gas prices. These are the forward curves reflected on Friday.

As we approach production at CP2, our pipeline infrastructure, which enables us to access Permian gas at Waha and Katy, is likely to become increasingly supportive of expanded margins. Importantly, Waha gas is expected to remain at a significant discount to Henry Hub, creating an opportunity for positive basis impact at CP2, highlighting the value of our investment in nitrogen removal units to address high nitrogen levels found in that basin. Flipping to page 20. Based on our bottom-up view of the global LNG market on the left, we expect demand to meet or exceed supply through the end of the decade, but quickly move to undersupplied early next decade unless additional liquefaction capacity is added.

This positively supports contracting demand for our growing portfolio. Importantly, these assumptions are conservatively based on demand growth of 4.7% through 2035, which is below the historical 5.3% from 2015 to 2025. Demand for clean baseload electricity continues to grow. New LNG markets are being developed throughout the world. Historically, demand for energy and certainly gas increases as price declines provided the physical infrastructure exists to support it, which we see on page 21, where we see some of the expansion of regasification infrastructure, which is further positioned to grow by approximately 40% from 2024 to 2030 with upside as new projects are announced. China alone is positioned to add more than 100 MTPA of regasification capacity by 2030.

India is committed to taking natural gas from just 6% of primary energy mix to 15% by 2030 as well. There has also been a sharp increase in developments from new markets like Iraq, Vietnam, Philippines, South Africa, New Zealand and others. We see countries around the world increasingly require reliable, consistent sources of energy, seek alternatives to cross-border pipelines, and make investments to meet rising power demand. Furthermore, we estimate regasification utilization would only need to reach 40% of capacity in order to offset all of the new liquefaction infrastructure currently under construction, which again is seeing slippage in FIDs and projected startup timing. Page 22 reflects the growth in gas-powered generation in both Europe and China. Not only are investments being made in regasification infrastructure, but also in gas power generation, which we expect to experience heavy utilization, particularly at attractive LNG prices.

In 2025, a high price global LNG market, less than 3% of Chinese power was produced from natural gas, while more than 55% came from coal. As existing installed gas generation capacity operates at higher capacity factors and new gas-fired power generation is added, we expect LNG imports to follow as delivered if LNG prices moderate. Domestic gas production is flattening in China and new pipeline additions are limited. Furthermore, we estimate that every 1% share gain by LNG relative to coal would translate into 34 MTPA of LNG demand. At $10 per MMBtu LNG prices, for example, the cost of electricity in China is about $0.07-$0.08 a kilowatt hour, converging on the cost of coal-fired power generation. History has proven that people consume affordably priced electricity.

In the event the LNG prices were to fall below $10 per MMBtu and gas and coal power generation approach parity, we would expect a sharp demand response, creating an LNG price floor at levels supporting liquefaction margins well in excess of those reflected by current long-term SPA prices. Of course, we’re in moments of price volatility, but we expect those, of course, as we move beyond current events, for them to smooth out. Consequently, we are confident that the market is building the infrastructure to easily absorb new LNG supply, and demand elasticity should mean every drop of LNG the market would be able to produce over the next several years should be consumed at reasonable prices. As evidenced by the forward curve historical precedent in contracting activity, our customers feel the same.

I’ll turn it over to Jack, our CFO, who will review the financials and our updated guidance.

Jack Thayer, Chief Financial Officer, Venture Global LNG, Inc.: Thank you, Mike. Pardon me. Good morning to those on the line. I’ll be referring to the Venture Global LNG, Inc. Form 10-K for the year ended December 31st, 2025. The 10-K is available on our website, and some of the key results are summarized on page 24 of the presentation. During this call, I will highlight results I believe are salient to this audience, and I encourage you to review the entirety of our financial statements in detail. Beginning with revenue, our top line was $4.4 billion for the fourth quarter of 2025, a $2.9 billion increase from $1.5 billion during the equivalent period in 2024.

This increase in revenue was driven by $3.8 billion from higher sales volumes, 478 TBtu in the fourth quarter of 2025, compared with 128 TBtu in the fourth quarter of 2024, which was partially offset by $945 million from lower net rates, primarily at Calcasieu Pass due to the commencement of LNG sales under its post-COD SPAs. For the full year 2025, revenue was $13.8 billion, up $8.8 billion from $5 billion in 2024, primarily due to increased sales volumes, partially offset by lower rates. Our income from operations was $1.7 billion in the fourth quarter of 2025, a $1.1 billion increase from $594 million in the fourth quarter of 2024.

This shift was primarily driven by the higher sales volumes I mentioned previously, which resulted in a greater total margin for LNG sold. These increases were partially offset by $50 million of higher operating costs in support of the ramp-up of LNG production at the Plaquemines project and operating our tankers, as well as $32 million and $147 million of higher G&A and depreciation expenses, respectively. We experienced a reduction in our development expenses of $72 million quarter-over-quarter as many of the costs associated with our three-phase CP2 project were capitalized. For the full year 2025, income from operations was $5.2 billion, up $3.4 billion from $1.8 billion in 2024.

Our net income attributable to common stockholders, which we will refer to as net income, was $1.1 billion for the fourth quarter of 2025, a $196 million increase from the $871 million in Q4 2024. Higher interest expense and changes in interest rate swaps negatively impacted Q4 results year-over-year by $330 million and $476 million respectively. For full year 2025, net income was $2.3 billion, up $0.8 billion from $1.5 billion in 2024. Shifting to Consolidated Adjusted EBITDA, we earned $2.0 billion during the fourth quarter of 2025, a $1.3 billion or 191% increase from $688 million in Q4 2024.

This increase in Consolidated Adjusted EBITDA was driven chiefly by higher sales volumes, partially offset by lower prices. For the full year 2025 Consolidated Adjusted EBITDA, we earned $6.3 billion, a $4.2 billion or 198% increase from $2.1 billion in 2024. The increase in Consolidated Adjusted EBITDA was again driven chiefly by higher sales volumes, partially offset by lower prices. Our projects exported a total of 128 cargos at Q4, which increased by 95 cargos compared with the same period in 2024. Of these cargos, 478 TBtu of volumes are reflected in our results for Q4 2025, more than tripling production compared with 128 TBtu in Q4 2024. I would also like to call out several additional financial updates.

The company issued $3 billion of Plaquemines notes in the quarter, which in combination with the proceeds from interest rate swap breakages, we used to repay $3.2 billion of the Plaquemines construction loan. For the year, we raised $33 billion in support of our development and to refinance existing debt. During the quarter, we secured a new $2 billion corporate revolving credit facility, which was undrawn at year-end. For the full year 2025, we reduced total leverage at Calcasieu Pass by $190 million, and at Plaquemines, we reduced total leverage by $919 million. Moving to project performance and forward guidance, on page 25, we are looking to produce between 486 to 527 cargos from both facilities in 2026.

Including volumes sold under our long-term SPAs, we have now contracted 69% of potential 2026 cargos. In the fourth quarter at Calcasieu Pass on the 38 cargos exported, we realized an implied weighted average liquefaction fee of $2.01 per MMBTU, which incorporates arbitration-related reserves. For 2026, based on average liquefaction fees achieved from SPAs and excess cargos sold on a forward basis to date, we expect an implied weighted average liquefaction fee of $1.98 per MMBTU at Calcasieu Pass, including an adjustment for arbitration reserves. For the full year 2026, we expect to export 145-156 cargos.

At Plaquemines, the facility exported 90 cargos at a realized weighted average liquefaction fee of $6.02 per MMBTU on our commissioning cargos during the fourth quarter, which was negatively impacted by a brief period of margin compression in December as Henry Hub prices escalated, shipping day rates increased, and TTF remained largely static. The shipping impact was partially mitigated by our owned and chartered fleet, demonstrating the advantages of maintaining a fleet of controlled vessels. In total, Plaquemines exported 234 cargos in 2025, which we expect to rise to 341-371 cargos in 2026.

This wider than normal range of potential production is driven by the inherent variability in the commissioning process as we prioritize the completion of construction and commissioning and address any remediation items through the startup process, which may cause brief periods of interruption. Thus far, including phase 1 COD in Q4, Plaquemines has contracted 59% of potential cargos for the year, capturing a weighted average liquefaction fee of $4.05 on those contracted commissioning cargos and fourth quarter SPA cargos. As you see on page 26, based on this cargo count, we are providing consolidated EBITDA guidance for a range of $5.2 billion-$5.8 billion for 2026.

This range assumes a liquefaction fee of $5-$6 per MMBTU for cargos remaining to be sold over 2026, consistent with current TTF and JKM forward price expectations as of Friday. On average, if fixed liquefaction fees over the remainder of 2026 increase or decrease by $1 per MMBTU, we expect our Consolidated Adjusted EBITDA range to adjust accordingly by $575 million-$625 million. We do not typically provide quarterly Consolidated Adjusted guidance and do not intend to do so in future quarters as you’ll see on page 27, we did wanna provide some color with respect to the impact of Winter Storm Fern as well as a residual impact of margin compression in late Q4 2025.

Relative to a $5.50 per MMBtu liquefaction fee on our available capacity, we estimate higher Henry Hub prices, the absence of several foregone cargoes, and basis impact at Plaquemines will have had approximately a $500 million impact on Q1 2026 Consolidated Adjusted EBITDA, which we now expect to range from $1.15 billion-$1.25 billion. I will now turn the call back over to Mike.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Thanks, Jack. Before I turn to questions, I want to address the concerning situation unfolding in the Middle East. We are monitoring developments closely and hoping for the safety and security of all Americans and everyone else in the region. The events over the weekend have had a strong impact on global energy markets. With the largest available incremental LNG capacity in the world, the United States will play a critical role during this historic disruption in the market. Venture Global stands ready to help keep the market stabilized and supplied. I’ll now stand by for questions.

Unknown Operator, Conference Call Operator: Thank you. We’ll now begin the question and answer session. Please limit yourself to one question and one follow-up. If you would like to ask a question, please press star one on your telephone keypad. To withdraw your question, please press star one again. Please pick up your handset when asking a question. If you are muted locally, please remember to unmute your device. Please stand by while we compile the Q&A roster. Our first question will be coming from the line of Neil Mehta from Goldman Sachs. Neil, your line is now open.

Neil Mehta, Analyst, Goldman Sachs: Hey, good morning, everyone.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Hey, good morning.

Neil Mehta, Analyst, Goldman Sachs: Thank you for the time. Hey, morning. Mike, can we start on the macro? I know you just touched on it right here. Maybe just any perspective on what you guys are seeing in the market right now, what are you watching for a read on what’s going on, how long the Qatar disruptions could last, et cetera? Then kind of connected to all of this, just walk us through a little bit of what your ability to transact against these current prices could look like. Thanks.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: No, obviously, it’s a sad situation in the Middle East and, you know, we’re hoping for a fast recovery. We have a very long-term view on the market, which is that low and stable LNG prices increase demand over time, and our business model is designed to deliver, you know, deliver low-cost LNG into the market. In the short term, the higher prices are, you know, helpful for our spreads, obviously. We probably have the largest number of available cargoes in the market. You know, on Friday, it was us and Qatar that had the largest available volumes.

So, so, with Qatar for the moment, turned off and potentially damaged, the market’s waiting to see if there can be an estimate on when it can turn back on and the ships can start to flow through. Obviously, the price in the market with physical commodities is based upon the, you know, the price of the last available physical cargo, and the market’s gonna take a few days, I think, to digest what that, what that looks like. Europe, as you know, has been and is at fairly low historic levels of storage, and so this is not helpful timing. Though spring, you know, spring is around the corner in a few weeks here, so that should help there.

There are markets in Asia that are also heavily reliant on Qatar supply and, you know, every day that ships can’t flow through, that creates a lot of backup and incremental demand. We are unique also in that we have our own fleet of ships with owned and leased. We’re 10 ships and we excuse me, nine ships. We take delivery of two more here in coming months. We’re uniquely able to move cargoes with our own vessels in this market. While TTF and JKM have spiked, so have shipping rates. Shipping is gonna play a very critical role in kind of support of the market and having impact on the ability to move the cargoes.

Neil Mehta, Analyst, Goldman Sachs: I appreciate that, Mike. I wanna look a little longer or a little more medium term to the back of the decade. You guys are laying out a pretty large construction plan, a fair amount of CapEx, of course, associated with that. Can you again walk us through kind of what your funding plans look like right now, and how much of that plan to get to, you know, mid-eighties or somewhere into the eighties on capacity is based on an assumption of higher prices in the market? Thanks.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Yep. The none of it’s based on higher prices. We with we can comfortably execute it with attractive returns at the, you know, the long-term contracts that we have. And the ones that we’re working on and that price on the commissioning cargoes as well. The we’re working as we said to hopefully finish up the second phase FID for CP2. As we guided to, we currently don’t expect to use any parent debt preferred or common equity, just at the project level construction loans and retained earnings. For the bolt-ons, which after the second phase of CP2’s incremental kind of 13 plus MTPA, we expect again to be able to use retained earnings and construction loans leveraging incremental contracts as well.

From a capital standpoint, our plan today and our expectation is that we’ll be able to finance that incremental CapEx without tapping parent capital materially again and retaining 100% ownership of that growth. That’s, as I said in the opening statement, with those two bolt-on transactions would get us to that, you know, 90 cargoes a month in 2029.

Elvira Scotto, Analyst, RBC Capital Markets: All right. Thanks for the time. Appreciate it.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Yep.

Unknown Operator, Conference Call Operator: Thank you for your question. Your next question comes from Manav Gupta from UBS. Your line is now open.

Manav Gupta, Analyst, UBS: Good morning, Mike and team. My first question is we recently saw a filing by you, which you basically indicate that you would be in a position to run Plaqu even at 35 MTPA and maybe CP2 at 35. I’m trying to understand how are you able to find these incremental volumes in your system? Is it the engineering? Is it the design? Is it operational efficiency or the massive data operations that you have set up? Help us understand how are these incremental volumes available in the system.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Good morning, Manav. Thanks. We really designed the facilities to physically and safely be able to operate at that capacity of 35 MTPA if conditions support it, which means during the cold months, we’re able to operate at that level. On an annual level, that would work out to around 31 MTPA for the year. The facility from a safety standpoint and a throughput capacity could operate at 35 for the whole year if it were cold for the whole year. When you average it out, at that level, it would operate 31 MTPA. The way we’ve achieved it is a combination of lots of adjustments we’ve made from CP, from CP1 to Plaquemines and CP2, and it’s a combination of how we’re managing pressure and our modularity and our controls.

I would say it is almost all driven by the massive amount of data collection that we process. I think we’re now capturing over 500,000 data collection points every 10 seconds between Calcasieu Pass and Plaquemines. We have a large data science team and AI programmers that consume that data and incorporate it into our operations and our process design. It’s we’ve achieved, you know, extraordinary dividends from it. We’re extremely pleased. We are able to, particularly ’cause we have so many trains and that we operate now, that we’re able to experiment with changes in conditions and configuration that allow us to fine-tune production.

Manav Gupta, Analyst, UBS: Perfect. My next question, Mike, is more on your vision. We will see a big build-out of LNG. How do you see Venture Global position in it? You are the low-cost provider. We also see you as somewhat of an industry disruptor, which is basically going out there and asking a question that why should it take 6 years to develop an LNG project when it can be done in 2 or 3 years? The reason I’m also asking is there were some competing LNG projects which are basically saying, "Okay, we don’t actually want to do this anymore." Maybe that’s a function of they really cannot compete against people like you. Help us understand your vision for the company in the massive LNG build-out that we’ll see in the next 4 or 5 years.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Thanks, Manav. you know, I, I think our space is the same as many other spaces when there are new business models and disruption in different categories. The incumbents in existing parts of the market react to it. So, you know, we obviously in our industry all produce the identical product, the same, you know, liquid methane commodity, and it’s largely differentiated on price. We do have a significant price and speed advantage, and we are bringing on large volumes of the cheapest liquefaction in the market, we believe. That will inevitably have an impact on people making decisions to invest capital to expand production capacity that in some cases would be multiples more expensive than what we’re bringing on.

We do expect it to have a deterrent impact. As we come into the market. We will, you know, in the future because we’re bringing on volumes at scale, we’ll have a positive impact on lowering the price which as I mentioned a few minutes ago, we like because we, part of our mission and part of the satisfaction we get out of what we’re doing and working so hard is to lower global energy prices. Over time, that fundamentally increases demand for us. Since we’re able to add so much more volume, we make money for shareholders, you know, with volume even if prices compress.

Julien Dumoulin-Smith, Analyst, Bank of America: Thank you.

Unknown Operator, Conference Call Operator: Thank you very much for your question. Your next question comes from Elvira Scotto from RBC Capital Markets. Your line is now open.

Elvira Scotto, Analyst, RBC Capital Markets: Hey, thanks. Good morning.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Good morning.

Elvira Scotto, Analyst, RBC Capital Markets: I know you talked a little bit about the macro, but maybe a little bit more here, especially as there are concerns around a supply. I mean, obviously, you know, current events not, notwithstanding. You know, you talk about lower prices driving demand and coal to gas switching. Can you talk a little bit more about that? And, you know, prior to the events of this weekend, were you actually seeing incremental demand as TTF for global prices moved lower?

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Yeah, no. No, thanks for that question ’cause that is actually one of the important things that we wanted to talk about on this call. Is when, you know, when we look at the market in the next, you know, 4 or 5, 6 years, we see when you map out the new projects that are projected to come online and demand that’s the same or slightly below what it’s tracked for the last 10, 15 years, which is over 5% annual growth, that the market is in balance to a little bit short in the next few years. You know, in the early 2030s is very short. Of course, if projects are delayed, then the short gets more significant.

Even with that current balance, which the market, you know, all can see the projects that are coming, the market, you know, net spread today as of Friday was between $5-$6. You know, as we announced this morning, we just did a very attractive 5-year deal, at BGC, and we’re working on more of them now, that really belies the argument that there’s terrible spread compression coming. We think that based on what we see in the market and demand, that in fact the markets look really steady. Over time, the replacement cost of liquefaction capacity is gonna set what the floor price is.

We think the global cost of new new liquefaction capacity is more north of $2,000 a ton when you take global costs into account. You know, at that price, you really need $3.50-$4.50 minimum for long-term contract prices to support returns. Now, on the question of downside protection, you know, it’s I think it’s obviously empirical that when energy prices go down, demand goes up. It’s been the case in human history other than, you know, pandemics. The question is there a physical infrastructure in place that allows for increased demand as prices go down? The answer is absolutely yes. You know, the market today has a lot more regas capacity than it utilizes.

I think in the next couple of years, the market will approach over 1,500 million tons of regas capacity globally. You know, a good estimate for 2030 market supply is around 620 MTPA. The market’s almost triple regas capacity relative to supply. There’s plenty of capacity for prices to have an impact on demand as they go down. We also always like to point out, you know, what’s the converted price of the delivered fuel to a market into electricity. You know, at a $10 MMBtu price into China, for example, or Asian markets, that’s, you know, $0.06-$0.07 or so, $0.08, depending on the market, kilowatt-hour electricity. That’s extremely attractive. Similar for Europe.

Historically, electricity prices and, you know, by corollary, fuel prices at that level are bought at full production capacity. We’re very optimistic on what the prices are gonna be in the next few years, and we’re seeing it in our contracting activity. We don’t need it to be there, but we just believe that it will average there and average higher. As I said in the script I just read, because we’re adding so much volume of liquefaction trains at even low prices, you know, at $3 per MMBtu in the next few years, that could equate to $11 billion of EBITDA in 2029 with the extra trains.

At $5, which we think is very possible too, that would be $17 billion, which is a reflection of just the massive scale of trains that we keep adding. I know that was a walkabout, Evira. Hopefully, that was helpful.

Elvira Scotto, Analyst, RBC Capital Markets: Yeah. No, that was very helpful. You touched on it a little bit, but, on the contracting side, so you announced these two new contracts in the past few days, this 20-year SPA with Hanwha and the 5-year contract with Trafigura. Can you talk a little bit about pricing around those contracts? How do you see the appetite for long-term SPAs? Finally, remind us the mix that you target between long-term, medium-term, and short-term contracts.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: The Hanwha contract, we haven’t disclosed any specific prices on it, but it’s consistent with what we’ve been doing recently in our contracting. Our both our 20-year and our midterm contracting activity is very busy, and we expect more deals in coming quarters on both 20 years and on the midterm. The midterm contract is... I’m not gonna give the exact price, but it’s, you know, north of a $3 net spread over 5 years. Relative to the 20-year, the 20-year contract price, very attractive for us. Again, just illustrates the demand in pricing in the market relative to what some people view as significant compression coming, which we disagree with.

We’re very busy on both midterm and the long-term contracts, and we expect that to continue. We’re almost at 50 million tons of 20-year contracts and which is you can’t see me, but I’m doing air quotes, is right around the nameplate capacity of CP1, Plaquemines, and CP2. On a traditional nameplate capacity, which it doesn’t apply to us anymore, we’re almost fully contracted on a 20-year basis, which allows us to right size the construction loans that we use to support those projects at coverage levels that give us the same debt coverage that the rating agencies want to see that will allow us to be investment grade around COD for the projects.

From a debt coverage, both, you know, debt amortization and interest coverage, we’re the same as the rest of the market. Of course, we produce a lot more than that gives us enormous upside optionality and, you know, I’m doing air quotes again, you know, very free to cheap capacity. That will begin to pay us dividends. I mentioned it briefly in the script, but in the case of CP2, we invested heavily and foresaw the opportunity almost 3 years ago now, to access gas directly from the Permian from Waha all the way to CP2. We’ve invested massively in large scale Nitrogen Rejection Units. I think it’ll end up being over $1 billion that’s been invested.

Pipelines along lateral CPX and a Blackfin pipeline that interconnects, it takes us all the way to Katy. Transportation agreements that physically connect us to Waha. That combined with the nitrogen removal unit, make us unique as the only facility that can take massive direct volumes from Waha to our facility and handle the large amounts of nitrogen efficiently. We’re feeling good about it. That was 3 years of engineering and design work and execution.

Elvira Scotto, Analyst, RBC Capital Markets: Yeah. Great. Thank you very much.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Sure.

Unknown Operator, Conference Call Operator: Thank you very much for your question. Your next question comes from Christopher Snyder from Deutsche Bank. Chris, your line is now open.

Christopher Snyder, Analyst, Deutsche Bank: Thank you, operator. Good morning, Mike.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Morning, Chris.

Christopher Snyder, Analyst, Deutsche Bank: Just like going back to the long-term SPA agreement signed this year and last. I know you’re not commenting directly on pricing directly. Can you comment around the directionality, let’s say, of the liquefaction fee over time? Has that been fairly range bound over the past few quarters, or has that moved up kind of due to a rising tides lifts all ships type of market environment here?

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: We’ve been holding it steady deliberately because we’re able to provide attractive returns at that price, and we’re able to execute the volume of contracts that we want. That’s, we’re at a significant discount to where we think the rest of the market is getting priced, and we’re gonna maintain our levels, because we have a lot of volume that we can build very attractively. At those price points and, you know, this is a culmination of, you know, 12, 13 years of work for us to build out the team and the supply chain and the sites to be able to continue to do this.

We’re gonna continue to add the 20-year deals at prices that are very nice returns for us and allow us to continue to grab market share. You know, we’re excited to add the liquefaction trains very cost effectively that give us the higher volumes of production capacity that regardless of kind of the price volatility generate enormous amounts of free cash for us.

Christopher Snyder, Analyst, Deutsche Bank: Thanks for that, Mike. Yeah, following up on a few of the points there. Just looking at the expansionary nature of the CP2 and Plaquemines bolt-ons, kinda how are you thinking about, is there a change in calculus a bit on the amount of long-term contracted coverage or nameplate capacity on long-term contract required by the lenders? I guess if so, what are you targeting in terms of total contracted nameplate on those expansion projects? How should we think about expected CapEx on a dollar per MT basis, just given their nature of not being new build assets, but expansions?

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Thank you for that question. Our primary focus after the second phase here of CP2 are the two discrete bolt-ons, one at CP2 and one at Plaquemines. They’re, you know, 4, 8 train, 4 block, 8 train additions that marry up really well with the existing balance of plant. As you said, allows us to do it very cost effectively. We expect it to be a significant discount to the already good price that, or cost that we’re able to achieve. Also, we’ll be able to build it faster because there’s a lot less that goes with it. They’re each around 6.5 million tons each.

After those, you know, we’ll watch the contracting progress of our 20-year deals and our 5-year deals to see, you know, what the expansions are after that. We’re focused primarily on those two discrete projects because they are so much less expensive and so much faster. We designed phases 1 and 2 for CP2 and Plaquemines to anticipate them. In particular for CP2, it’s inside the existing wall and the pipe bracket connections are very short. It will go in very quickly and very efficiently. That those bolt-ons will allow us to get to that kind of 81-85 MTPA in early 2029.

Again, we need to keep pace with the permitting, which is very good, strong in this, in this, in this environment. With our existing supply chain and our teams and our sites, we can layer that in very quickly and start to produce from them later in 2028 and 2029 that will, you know, get us to that in a roughly 90 cargos loading a month in 2029.

Christopher Snyder, Analyst, Deutsche Bank: Thank you, Mike. I appreciate the answers. I’ll turn it over.

Unknown Operator, Conference Call Operator: Thank you very much for your question. Your next question now comes from Julien Dumoulin-Smith from the Bank of America. Greg?

Julien Dumoulin-Smith, Analyst, Bank of America: Good morning, everybody.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Hey, Greg. Good morning.

Julien Dumoulin-Smith, Analyst, Bank of America: Good morning, everybody. Hey. Good morning. I think you just as you laid out very nicely that you don’t have capital expectations at the holding company between equity and debt. Just talk a little bit if sort of at the project level, if things have changed a little bit. Are you still planning on funding 50/50? Just talk about the appetite for banks to support that.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: The appetite of the banks on the construction loan side is extremely strong. Our the quality of the execution by the teams in the projects is appreciated by the banks. Since we’re largely building identical things and process systems at all our facilities and projects, the bank capital market can understand it well and has great visibility into kind of tracking progress. That’s supported us in having very efficient access to the bank capital markets. You know, we expect that to continue to be the case. We have already invested a lot of equity just from retained earnings into the second phase of CP2. When we finance that second phase, it’ll become one financing.

We don’t expect to have to add, at this point, capital from the parent to support it. It’ll be construction loans, existing capital invested in retained earnings. After that, this coming phase two, the bolt-ons are unique because they’re less expensive and they turn on even faster. You know, don’t hold me to this or don’t invest based on this. It’s a forward, it’s a forward-looking statement. You know, it’s roughly, you know, 20 months or so to turn on the bolt-ons because there’s so much less kit that is required to do those bolt-ons. When you produce revenue so quickly and earnings so quickly on those bolt-ons, it gives you a lot of flexibility in how you can finance at the project level those sites.

The combination of speed and lower costs gives us lots of really attractive options about how to add it and how to contract it in the market.

Julien Dumoulin-Smith, Analyst, Bank of America: Got it. Maybe just last one from me. Obviously, you have had some success with the arbitrations as of late. Just how are you thinking about that as part of your funding plan, and just to the extent you settle anything and just a reminder on timing for when you think we’ll actually get some numbers from the BP process?

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: There is no hearing expected to be set for BP this year, so that process will play into next year, probably later next year, before there’s any further developments there. We expect the next results on the arbitration front. We can’t predict them because we’re not in control of the deadlines, but in coming quarters and on the back of the very successful unanimous result on the Repsol, the Repsol win, you know, we remain positive on outlooks for the remaining arbitrations. We’re hoping to largely have resolution in the next few quarters and have it all behind us.

Julien Dumoulin-Smith, Analyst, Bank of America: I appreciate the time, guys. Thanks.

Unknown Operator, Conference Call Operator: Thank you very much for your questions. There are no further questions at this time. I will now turn the call back to Mike Sabel, CEO, Executive Co-Chairman, and Founder, for closing remarks.

Michael Sabel, Chief Executive Officer, Executive Co-Chairman, and Founder, Venture Global LNG, Inc.: Thank you, everybody. We appreciate the time this morning, and we look forward to conversations in coming days with all or many of you. You know, we’re gonna be working hard for everybody, through these challenging and volatile markets in parallel with all the construction activity that continues. Thanks again for the support, and look forward to seeing and speaking with you soon.

Unknown Operator, Conference Call Operator: This concludes today’s call. Thank you for attending. You may now disconnect.